Hello Experts,

Do you know if there's a way to block only the dates programin for the users?

For example: I have a project with 2 taks, taks 1 and task 2.

Task one starts day 01/12/11 and finishs on day 02/12/11. Task 2 starts on day 03/12/11 and finishes on day 04/12/11.

I want to allow some users to acess that project, with write enabled, for adding material, or some other info, but blocking the possibility for those users to change the dates of the tasks (reprograming).

Is there any way to do that?

Thank you!

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

It is possible through Screen varient in Tcode SHD0.

with regards

M Umapathy