Hi Experts,

As per our client requirement we marked price control "S" for all materials. While running the Std costing, system is showing the Cost components as below

Direct Material 13.29$

Material Overheads 1.92$

Direct Labor 68.19$

Labor Overheads 79.78$

The Material overhead percentage rate is 16.9%.

Now the problem is with the Material cost 13.29$. In this cost the Material overhead cost also included. So please suggest what i need to change in the config part to get this component (Direct Material) without material overhead.

As per our requirement the values should be shown as below

Direct Material 11.37$

Material Overheads 1.92$

Direct Labor 68.19$

Labor Overheads 79.78$

Thanks&Regards,