Dear Experts,
I am using SCM APO 7.01.
The scenario is as follows:
Product A can be produced from 2 alternate PDS.
I have maintained the following in the inbound quota arrangement in 000 dependent version.
Header level for product A:
-
Req split indicator
Min split quantity 100 TO
Item level
-
PPDS PDS1 40% Quota arrangement
PPDS PDS2 60% Quota arrangement
PDS1 Quota base Qty 100
PDS2 Quota base Qty 100
Heuristic
PDS1: SAP_PP_Q001
PDS2: SAP_PP_Q001
-
Maintained SAP_PP_Q001 in the product master PPDS tab as well.
Invariably changing the heuristic in the quota arrangement or even changing that in the product master,it does not help much.
When I take a heuristics run in the product view for product A,it just selects PDS1 and produces the entire quantity of 1000 on this.
When taking the run from production planning transaction as well,the result is the same.
Could you suggest if I am missing anything.
Thanks,
Chandan Burnwal