Hello Gurus
I have a material say XXXX with its MAP as 18,682.10 say
the quantity of the material is 2 lying under project stock so as per MAP the value of the material will be 37,364.20
when i run MB5B for this material it is showing as 1,37,364.20 there is a difference of 1,00,000 between the Actual value.
The reason is at the time of initial upload My client intentionally or due to some financial settlements uploaded an extra amount of 1,00,000 to the material which didn't effect the MAP because the stock is uploaded to the Project Stock.
Now the Issue is he want to reduce the value of extra amount added intentionally, or he want to devaluate the prices of material
how should i process this, please provide me some solution for this.