Time dis aggregation at CVC level

Hello,

We have a requirement where we need to dis aggregate the quarterly buckets into monthly buckets based on percentages.

CVC Quarter KF % split into ( Month1,Month2,Month3)

1 1 100 (20,30,50)

2 1 100 (40,20,40)

3 1 150 (50,30,20)

Now the requirement is to split the KF based on the selection. Is this possible in DP? If we have more than 100 selections which need this kind of dis aggregation how can we address this?

APODPDANT can do the job at planning area level. But if it is selection level how do we do this.

Any input is highly appreciated.

Thank you,

Sai.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 07, 2011 at 08:01 PM

    Never mind, i figured the answer.In the first place i think i framed the question wrongly.

    The solution would be to use time dis aggregation based on History Key figure. So We just assign this KF to the forecast KF. When the forecast is run the KF takes its proportions from History KF.

    Closed,

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.