There is still purchase requisition commitment for WBS element.

Hello all,

When i try to close the project i m getting the error message " There is still a purchase requisition commitment for WBS XXX "

I checked by running the report "S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned" . i found that commitment column '0'

Again i ran report "S_ALR_87013537 - Commitment Detail " to cross check the commitment.In this report both PO and PR commitment are visible.

My question is why there is a difference between these two reports???

Because of this i m not able to close the ticket.Please help me.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 07, 2011 at 06:54 AM

    Search the forum. This issue has been discussed many times in this forum. There are certain correction programs that you need to run to rectify this inconsistency.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 08, 2011 at 01:11 AM

    Watch this thread Wrong commitments value for a wbs element

    regards

    M Umapathy

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.