Dear All,
We've faced with issue for dynamic price update.
We have customized it there Controlling -Product Cost Controlling -Actual Costing/Material Ledger -Configure Dynamic Price Changes.
We have loaded beginning stock of finished goods in november.
Than we have created and marked cost estimates for december in ck40n.
However, during first movement in december the price for materials was not updated. Cause the material state for december is Quantities and values entered. That status material get after upload of beginning stock values in previous period.
That happens in release 6.0.
And that didn't happen in release 4.7.
We need price to get updated automatically in december.
How we can do it if we have uploaded values and quantities in previous period?
With best regards,
Kamila.