Clarification in Dates tab in WBS

45 Views

Hi,

i am facing some difficulty with Dates tab in WBS.

I created a project using CJ20N and then i created a WBS but in the dates tab the values for early start, early finish, latest start and latest finish are automatically scheduled which i dont want to happen.

i did check parameters for WBS Scheduling and unchecked Automatic Scheduling and also unchecked automatic scheduling in parameters for network scheduling using OPU6.

Please guide me in the same