Job failing after start of process chain

Former Member
0 Kudos

HI All

i have proces chain based on sm37 job....but the chain is stucking at the Start process of the Proces chian and the Start process is in yellow...

when i check the status of the job in sm37.. it is showing as cancelled and it is showing in Release status for the next day.

When i check the job log entries for the job, it is showing the below message:

Job started

Step001 started (program rsprocess, variant&00000, user id xxxxxx)

" Process ABAP, Variant Delete_SLA_sales_complete is not scheduled waiting for event RSPROCESS 4DYXXXXXXXXXXXXX "

job cancelled

How to solve the above issue...?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Go to the variant in your process chain and make sure they are trigger from previous step or chain

Pls assign points if this was useful

Answers (3)

Answers (3)

former_member182470
Active Contributor
0 Kudos

Hi,

Your process chain has been scheduled repeatedly by using Repeat Scheduling option in RSPC. Then the Start Variant will remain in yellow. You need to make the released job to scheduled by getting into Planning view.

Regards,

Suman

Edited by: Suman Chakravarthy on Dec 7, 2011 11:22 AM

Former Member
0 Kudos

the issue is that the variant is out of schedule. right click on you rprocess chain and make sure it shows scheduled job. go to the variant in yoru process chain and make sure they are triger from previous step or meta chain .. you can also view in detail on the process chain on top menu from view.

Former Member
0 Kudos

Hi,

Can you check the background job is scheduled for that particular variant or not?

Thanks

Riyez