hi experts,
My client ask me to schedule the process chain for 3 times in a day, because client has plants in EUROPE,USA,AUSTRALIA.
The process chains must run 3 times per day e.g. 00:15, 07:15 and 14:15.
How can i schedule the process chain specified like everyday at 00.15, 07.15 and 14.15 hours (these hours based on EUROPE).
but in the process chain variant we can schedule in the other period for hours, but as asked by client above hours how can achieve ?
please provide the solution..
Regards
Venuscm