Basic finish date earlier than basic start date while backward scheduling

38 Views

I am encountering an issue where in when I am selecting backward scheduling for a process order and I am entering the Basic finish date, afte which system is giving me a Basic startdate which is after the basic finish date.

For eg:- When i give the basic finish date as 08.12.2011, system is giving me basic start date as 09.12.2011

I have checked the recipe of the material. In the recipe one major flaw that i found out was that all the activity timings were maintained as 0. But when i created a similar scenario in the testing client, i am not getting the issue.

Please help.