Hi
I have create process order for 5000 qty and released ...
if i goto COR6 for conformation process order
(5000 qty = activity 1 --5 hours required as per Planned is maintained in Master recipe)
1)if i goto COR6 for conformation process order :
enter order number and opearation/phase no .press enter .. then enter yeild qty 2000 qty then press enter but system does given automatically activity1 value 2 hours for 2000qty yeild .
2)if i go through COR6N for process order conformation.:
enter order number and opearation/phase no ... then enter yeild qty 2000 qty then press enter but system does not give any any activity1 value automatically for 2000qty yeild ..why ?
if i required automatic calcutation as per yeild qty .. ..what we can do could any one guide me in this issue.