I have run CK40N for certain materials. Out of the materials included in the CK40N, one material was taken and I ran the CK11N for the material.

While comparing the results of the costing from both CK40N & CK11N, I find different cost results. Why this is happening so ?

Accepted Solutions (1)

Accepted Solutions (1)

former_member588855
Active Contributor
0 Kudos

kindly check the following....

>r u using the same costing variant in ck40n and ck11n.

>what is the timing difference between the two runs.

>analyse the line item which is having different cost.

Regards

Divraj

Answers (2)

Answers (2)

former_member218048
Active Participant
0 Kudos

thanks for the input. The difference in the costing results was due to authorization issues.

Former Member
0 Kudos

Hi

Check the following.

1. Is status of the Costing Run is same for both ?

2. Check the Cost of each Semi finished goods in each of the run