Dec 03, 2011 at 06:45 PM

Delivaery Date in MRP PR

59 Views

Hi All,

How the delivery date is calculated in MRP generated?

Here is the scenario:

We have planned del time in material master is 14 days, GR processing time is 2 days.

PR has created on 23 Nov 2011, and it gave the delevery date 28.12.2011 how?

FYI: There is a contract where the planned delivery time is 28 days, and also there is a reservation for same material for 261 movment and the requirement date is 11.01.2012.

Could you please help to understand this calculation.

Thanks in advance.