Hi All,
How the delivery date is calculated in MRP generated?
Here is the scenario:
We have planned del time in material master is 14 days, GR processing time is 2 days.
PR has created on 23 Nov 2011, and it gave the delevery date 28.12.2011 how?
FYI: There is a contract where the planned delivery time is 28 days, and also there is a reservation for same material for 261 movment and the requirement date is 11.01.2012.
Could you please help to understand this calculation.
Thanks in advance.