Hi Gurus

I have a PO of 10 kg say and GR is done for 8, now the status of the PO is pending because there is 2 more qty to be delivered,

I finally found that my vendor is not going to send the remaining 2 qty, so i will have to short close PO, for that i have to unrelease the PO and check the DCI in the Item level Delivery tab.

Now my client requirement is he want to check the DCI Indicator without unreleasing the PO as many as possible at a time.

Is there any way to fill this requirement.

Please tell me the possible solutions.