Hello All,

To replicate scenario, I have created new material with minimum lot size 10 pcs and created independent requirement (LSF) and then created scheduling agreement.

Independent requirements as 8 pc for every day.

Now when I run the MRP and check in MD04, for the last requirement, planned order was raised for just 9 pcs, ignoring minimum order qty/minimum lot size functionality.

Just for information, Lot size -EX, MRP type PD, Strategy group 10 (though these factor doesnot influence).

Any more settings/customizing required?