Hi,
In production order of 10 EA, I have two operations. operation 0010 on work centre T1, operation 0020 on work centre D1.Co11N is done for operation 0010 for 4 EA.
Now rest 6 Ea of first operation has to be done on work centre T2 ( because T1 is brokedown).
Pls help how to map this? Else is there any option to enter a new work centre( work centre T2) in CO11N screen during confirmation?
Regards.