I have several change requests were a developer created and released two transports, but they only required one to move to production. The other one is not needed and they do not want to move. However, this is preventing me from completing / closing the change request. Solution manager excpects that all released transprots have to be migrated to prodution in order to complete the change.
Is there a way to force the change request to complete? Is there a switch or something I can update that makes the CR think that all transports have been migrated to production?