Hello,
We have issue with WBS planning.
My local company code currency is = RMB and controlling currency is = EUR and version=0 dependent of value date 01-01-2011 for exchange rate-M.
Now we are trying to do the WBS planning with EUR (Controlling currency ).
For exmaple :
WBS planning = 10 EUR ( exchange rate between RMB to EUR for today is = 9 )/ Version-0 / Fiscal year -2011 .
But system is considering the exchange rate always at 01-01-2011 from TCURR table. So our WBS planning currencies values in below.
EUR = 10
RMB = 70 ( 10*7 ) - Exchange rate between RMB/EUR taking from TCURR table at 01-01-2011.
for me, the correct value with RMB is = 90 ( 10 * 9 - as per as exchange rate today is = 9 ).