Hi Gurus,
We have a requirement in which to allow overdelivery in the production order. In the FG material we have already allowed overdelivery in Work Scheduling Tab. However, during confirmation, an error message appears in which it says that the COnfirmation quantity of the components exceeded the quantity in the reservation. With this COGI entries are created for the components and I have already received the FG Material.
Is there a configuration or in the material master which I can activate so Production confirmation allow over consumption of material? If there is no confirmation, any best practice to handle the overconsumed quantity?
Thanks,
Raymond