Dear Experts,
I need help about the following scenario.
Currently I am working on preventive maintenance in SAP ECC 6.0 system. I am trying to assign a maintenance item to a maintenance plan which has a maintenance item already attached .
We carry out the following steps:
1. I run transaction IP01/ IP42;
2. I enter the maintenance category and the strategy;the strategy in maint item and plan are the same.
3. in the tab "Item" I click the button "Assign more items";
4. system runs report RIMPOS00 (Display Maintenance Item: Selection Criteria) in order to select the item to insert in the maintenance plan. In this screen the followin fields are locked (we can not change them):
- "Maint. plan cat.";
- "Maintenance strategy";
- "MaintPlan assignment" and the radio botton is set on "without".
In this way if a maintenance item has been already assigned to a maintenance plan users can not select additional maint item using this assignement tab for the current plan.
how can we make this "make plan assignment to with/without" option instead of option "without" ?
Could anyone help ?
regards,
ebenezer