Dear All,
We have 5 direct activity types and 3 overhead activity types in the system.
Plan Overhead cost splitted perfectly aginst the 5 direct activity types based on the activity quantity,
but when it comes to actual splitting:
1.the system splitting the cost eually in NEGATIVE among the 5 direct activity types instaed of splitting to 3 overhead activity types
2. system considering the all direct activity cost as part of one overhead activity types.
I am unable to understand how the system is behaving while splitting actual overhead costs to direct activity types
Can sombody throw any light on this issue.
Regards
SU