Hi Guys:

in MRP Net requirements Calculation,

for Example If want Consider Schedule out Sales orders( requested Delivery Date 02/02/2012) which is determined by planning horizon( 6 months 06/30/2012) , Since this sales order is within Planning Horizon it will consider for MRP Planning.

Is it the Same case with PO i.e Based upon the planning horizon PO will be included/excluded in planning?

Also if for example my PO is due from the Vendor one PO is due in 03/02/2012 and other PO is 09/15/2012?

Thanks