Nov 30, 2011 at 08:19 AM

Reduce Budget for Plant Maintenance Order without PS

46 Views

Dear All,

Request help for reducing the budget of an Plant Maintenance Order. Overall budget for order is Rs. 1,00,00,000 and want to reduce the same to Rs. 46,00,000. Actual Consumption of budget is Rs.24,00,000. I tried reducing the order through Ko26 but getting the below mentioned error.

Overall budget less than cumulative budget

-55000366(Order) 46,00,000 < 1,00,00,000 (INR)

Message No. BQ106

Diagnosis

The total budget 46,00,000 INR in order 55000366 is less than the cumulative budget 1,00,00,000 INR

The cumulative budget is total of annual budgets.

Please help for the same asap.