Why PR can be created without Internal Order eing assinged

Former Member
0 Kudos

Dear SAP Gurus and Expert,

Would like to check with you that wht the budgeted PR can be saved with no IO required?

Thank you

Regards

Leonard Tan

Accepted Solutions (1)

Accepted Solutions (1)

ajitkumar
Active Contributor
0 Kudos

F type PR can be saved by givng cost center data instead of internal order number. it need a CO object , either cost center or order

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

For these please go to OME9 -> select account assignment F (order) ->details -> make CO/PP Order field as mandatory entry

Now try to create PR and check