project was set to TECO

Good Morning PS gurus,

Please advise in which transaction , we can see which date a project was set to TECO?

Thanks

MM

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2011 at 04:07 AM

    Hi,

    On cj20n once select WBS/proj defn. ->click on system status 'i ' icon then -> Extars->change document->all-> double click on system status you want to see detail.

    regards,

    SL

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Use TCode CN60 to view change documents for multiple projects. You will get additional line items for every change and therefore will need to filter your results based on your requirements.

      Please also ensure whether change document has been activated for the respective project profile (for further details search the forum on change documents).

      Regards,

      Ammar

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2011 at 04:10 PM

    use t-code SQVI, join the tables PRPS and JCDS. It will show the details of wbs wise & status wise dates.

    with regards

    M Umapathy

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.