Pls share your thoughts on this scenario, client makes FERTs based on customer PO but plan ROH in advance with FERT forecast. MTO scenario with PS 52 helps completely but FERT is not configurable material so I would like to go with MTS for long run. here confusion with what strategy to use since FERT and HALB should not be made before sales order creation but need to procure ROH in 3 to 4 months in advance.