Skip to Content
0
Former Member
Nov 29, 2011 at 09:47 AM

Third-Party Order Processing delivery date

727 Views

Hello everybody

I use Third-Party Order Processing for modeling the delivery by the vendor to the customer.

The PR is automatically generated from the sales order. In the sales order, in the schedule lines tab, the system creates two lines :

- 1 line with the date desirated by the customer with a quantity of 0 confirmed

- 1 line with the date calculated with the delivery time (3 weeks) of the vendor master, with the total quantity

When I saved the sale order, the PR generated has only one schedule line with the total quantity with the delivery date desired by the customer. Normally I should have the delivery date of the vendor (today + 3 weeks).

Is it normal ? Do I miss some customizing?

Thanks for your replies,

NP