Hi,
In production order, basic dates are coming what we are maintaining as in house production time in material master.
I want to maintain basic dates as per the quantity.
Ex: To produce 100 pc, in house prod. time will be 5 days. And if the order quantity is 200 pcs then basic dates should show 10 days.
In work scheduling view, I maintain base quantity and in house prod. Time. When I run MRP for order quantity of 200, basic dates shows 5 days only.
What is the purpose of having base quantity, in house prod. Timeu2026 in work scheduling view?