Hi,
This is very peculiar scenario. here in one plant when we run the MRP PRs are generated but the dates are too far. like we run the MRP in July its generating the PRs for December.
Issue- In MRP created PR's ; the Release date - field EBAN-FRGDT
calculates wrongly- Can be explained better with below
examples.
E.g 1-
Material: 153539
Plant: 0263
MRP Type: PD
Safety Stock: 11
Inventory was below safety stock when MRP ran. Why did
MRP push the
delivery date out to 07Oct11 when planned delivery time
was 30 days.
If purchasing requisition was created 20Jul11, I would
have expected
Release date to be immediately (20Jul11) and Delivery
Date to be 30
days into future - 20Aug11, Instead the release date is
pushed to 06th
Sep 11.
Purchasing Requisiton: 20172442
Delivery Date D 10/07/2011
Request date 07/20/2011
Release Date 09/06/2011
Pl. Deliv. Time 30
GR Proc. Time 0
Purchasing proc time- 1 day at plant level MRP SPRO
E.g 2
-
Material: 145350
Plant: 0263
MRP Type: PD
Safety Stock: 100
Inventory was below safety stock when MRP ran. Why did
MRP push the
delivery out to 07Nov11 when planned delivery time was
21 days. If
purchasing requisition was created on 26Jul11, I would
have expected
Release date to be immediately (26Jul11) and Delivery
Date to be
16Aug11.
Purchasing Requisiton: 20201601
Delivery Date D 11/07/2011
Request date 07/26/2011
Release Date 10/14/2011
Pl. Deliv. Time 21
GR Proc. Time 1
Regards,
Adwait Bachuwar