I am in a typical situation. Here we have activated internal order budgeting and availability control.
We had already posted few POs for Asset procurement few months back. In that Assets were correctly done. Now only we have created the Internal orders and put budget for them. These internal orders are now input in the Asset master data also.
Now when we look at the budget/commitment report for the internal orders, only the budget figures are appearing. The PO values (commitments) are not appearing.
I think this is because the POs were posted previously for the Asset masters data without integrating an Internal order in the Asset master at the PO posting time. Now only the Int Order is put in the Asset master and budget entered.
How can we bring these PO commitment values to the Internal order budget figures ?