Dear Experts,

I have created a work center A - Which includes 5 individual machines, In work center - capacity tab i have increased my machines(No. of indiv. cap. 5)

IN WORK CENTER CAPACITY HEADER :- I went to GOTO--> Individual capacities --> there i have defined my individual machines as machine1,...Machine 5.

Now i created manual production order in (co01). I have my work center - A with operation 10. When i go inside the operation details, In the cap reqt assignment i have splited my order quantity for all the 5 machines.

I went to confirmation screen(co11n) i cannot view splited quantity. It comes as the total order quantity for confirmation.But i need to get split order quantity by machine wise.

Please give solution on this issue.

With Best regards,