Skip to Content
0
Former Member
Nov 28, 2011 at 05:49 AM

strategy sequence for the valuation variant in OPl1

515 Views

Hi

When a process order had been created one of the raw material moving average price had been changed when compare to standard it is showing u2013value when compare the standard price in the itemization report of the order.

When we have issue raw material to the process order it is picking price moving average price form the material master of that material.

When I am settling the order it is calculating variance between the target price u2013actual price (standard price u2013actual price)

I have selected following strategy sequence for the plan valuation variant in opl1

Material valuation.

Moving average price

Plan price 1

Standard price

Valuation according to price control in mat. Master

I have selected following strategy sequence for the actual valuation variant in opl1

Valuation according to price control in mat. Master

Moving average price

Standard price

Plan price 1

I wanted to know whether the system is behaving correctly or not or do I need to change the strategy sequence.

For the activities it is picking correctly for the plan it is picking plan price and at the time of confirmation also plan price when I am doing revaluation it is picking actual price.

Thanks in advance

kareem