Hello All,
We use the CTP process while creating Orders, with Block Planning & an Immediate Planning procedure for FG & the SFG. To-date, our process has been to get Sales Order confirmation ONLY when the system could return a successful availability @ the FG (the Resource on which the FG is planned is Infinitely capacity) & the SFG, ( the Resource for the SFG is Block Planned) level.
However, recently, we've started observing that the system confirms the Sales Orders even when its unable to get the SFG Block date or its unable to create an Order for the SFG. This is a dangerous proposition & we don't want that to happen.
Any ideas for the cause of this behavior?
We use ECC 6.0 with SCM7.0.
Thanks in advance