Hi experts,

I'm a beginner for this field, Suppose there is a process chain called "X" which is used to extract the data from SAP R3 side for the purpose of getting the data for BI query called "Q1". "X" has been schedule to run every day in the night in BI side and also there are jobs have been schedule in SAP R3 by using the T-code lbwe. (they also runs once per day in the night)

According to above explanation, If I execute the BI Query today, I can view only up to yesterday data. Suppose I have updated some data in the tables at SAP R3 side today. therefore immediately I want to see the changes when I execute the BI query...

Can you explain me how can I do this? Please explain this in Step by step if you can.