bydesign migration of projects

Former Member
0 Kudos

Dear Gurus,

Does anybody have a clue what this error message is trying to say:

Start date missing from expense incurrence period

Please note that the expenses tab of the Migration template is not maintained at all.

Any Feedback is highly appreciated.

Kind regards,

klaus

lokesh2
Advisor
Advisor

Hi Klaus,

Please check if you have maintained any confirmed work in the 'works' tab and also check if the start & finish dates are maintained for the confirmed work.

You need to enter these dates for the confirmed work to overcome the error.

Thanks

Lokesh Sharma

Former Member
0 Kudos

Dear Lokesh,

You are absolutely right!

There were missing entries in the tab "work" in the columns for START_DATE_TIME and END_DATE_TIME. No further changes were necessary.

Thank you very much.

Kind regards,

klaus