Hi,

How to handle in house production time if there is no production order?

Scenario: For a production order, material ' A ' will be produced and GR will happen to stores. The stock will be sit in quality stock. After doing inspection the stock will be moved to unrestricted stock.

Here, i am getting basic dates from material master for production order. My production order finish date will be the sales order delivery date. For inspection, there is no production order, I want to maintain dates some where. How to handle the situation?

Regards / US

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 26, 2011 at 04:58 AM

    US,

    Some companies use Goods Receipt Processing time to accommodate time taken for Quality inspection.

    http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d294a44af11d182b40000e829fbfe/frameset.htm

    Best Regards,

    DB49

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.