Hi everybody

When I do CK11N, I have an error like this: CK 694 No structure could be determined for internal activity.

In OKTZ I have the flag on Primary Cost Component Split. Is it necessary?

In KP26, I defined plan price for Cost center and activity

The secondary element that I had defined for assembly activity is already assigned in OKTZ.

I don't know how to fix this error. Does anybody help me ? Please

Thanks.