We have 2 plants Say A1 & A2
From A1 we have to send 100 Qty to A2. Then from A2 we have to reject 20 and it should be sent to A1 again.
How to map it in SAP........Both A1 & A2 plants were in different areas.
Hi,
From A1 we have to send 100 Qty to A2. Then from A2 we have to reject 20 and it should be sent to A1 again
.
There are two option
1) again create STO PO from plant A1 to plant A2 for 20 qty
2) create return STO return PO from plant A1 t0 A2 for 20 qty
Regards
Kailas ugale
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Assume that you are A1 plant.
transfer material to A2 100 pcs and get back reversal 20 pcs from A2 into A1 with one step plant to plant transfer.
Regards,
Syed Hussain.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.