Dear Experts,
Please confirm me when i should release the planned order to production order to our shop floor.
1. Is it when all the materials are in stock ?
2. Is it by checking by RM delivering date coming from PO. I.e., if suppose my all RM delivery date are coming as 2.12.11 then today should i release the planned order to production order for date 3.12.11 for our shop floor.
3. Or other is any ?
Regards,
Hi,
What are you asking about creation of production order from planned order or releasing of production order from created stage.?
Conversion of planned order to production can be done according to planning activity of an organization but releasing of a created production should be done when we actually decides to run the production order into shop floor.
Material availability of a material is checked during creation and release but you can set your system not to allow release if material is not available in OPJK as per your order type.
Hope it helps.
Regards,
Alok Tiwari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.