In our organization, works order can have two types of settlement receivers (cost centers or internal orders). To report planned cost by receivers, we create automatically groups of works orders (by receiver) and uses standard transaction S_ALR_*.
But it works only if settlement is not modified.
Does one of you know a better way to report those costs?
Thanks
Hi,
Try MCKo, there you can get the planned costs as per orders or if you want to analyse a particular object then you can go for object analysis MCI7.
Hope it solves your problem.
Regards,
Lucky.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I don't want to report planned costs by maintenance objects but by receivers.
For exmaple: i have 2 work orders on the same receiver (cost center 1)
WO1 CC1 11/2011 500u20AC
WO2 CC1 11/2011 600u20AC
I try to report planned cost for CC1
Regards
Simon
Edited by: Simon Maes on Nov 25, 2011 11:31 AM
Hi,
Goto IW39-> give selection parameters (cost center/ order type/ order no.) ->execute
Goto Settings-> Layout-> current-> select planned cost (or any other parameters you need).
Goto List-> save as-> select target location and file type.
later on you can take its print out as cost report.
Hope it solves your problem. In case any issues, let me know.
Regards,
Lucky.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.