Dear Expert,

Here I am getting error "Source not included in list despite source list requirement " at the time of P.O Creation.

I maintained Source List at Plant Level, and i did all the settings and Prerequisite. Still i am getting same Error.

I searched all the forum Inquiry.

For your more clarification:

I did same setting in sand Box 250 Client, there scenario run Properly without giving Error, but in DEV Server Client 400 same

setting i did, but there i am getting Error.

Can any body Help Me.

I already Maintained Source list with Plant, Material, Vendor and Date Combination.

Can anybody Help me.........................

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Answered

JL23
Active Contributor
0 Kudos

the message just means that your PO data does not match with the source list data.

What kind of PO do you create? does it reference a contract?

if yes, is the account assignment category/item category the same as in the contract?

is PO creation and delivery date within the validity period of the source list?

hope you have not ticket the blocked indicator in the source list.

Former Member
0 Kudos

Dear Jurgan,

Problem is solved, Due to Server Problem i was getting.

Thank You.

Former Member
0 Kudos

hi,

check ur master data ,mm02, purchase tab, source list

and chek me03

hope this help u

Regards,

Ali

Former Member
0 Kudos

Ali Bhai,

Thank you for your Valuable Answer.

but I am not making source list at Material Level. and i already maintained Source List.

Problem is Solved, Due to Server Problem, I was getting.

Thaks A Lot Ali Bhai...........

Edited by: poisionl on Nov 25, 2011 7:22 AM

Former Member
0 Kudos

Dear poisionl ,

What you have mentioned I have checked in my system there is nothing in config to check

Just check your master data again

i.e Material master,vendor master,plant , P Org, validity

You will find the solution.

Former Member
0 Kudos

Hi,

Check the validity of the source in the source list and mark the source as fixed source.

Hope, this helps!

Reetesh

Former Member
0 Kudos

GOTO OME5 there u tick the chk box against ur plant now try to create the PO and see whether ur getting the Error msg or not..

Former Member
0 Kudos

Dear Reetesh,

I am not going to FIX that Vendor for that Material.......................so That is not a answer, anyway that problem is solved.

It was happened due to Server Problem.....Table is not updating Properly at same time.............

Thanks for your Valuable Answer.

Thanks a Lot.....

Former Member
0 Kudos

Pranav ,

That I already Checked ........................any way problem is solved, Due to Server Problem. Table was not updating Properly........................

Thank You Pranav for you Valuable Answer.....................