Hi team,

1. Procurement of the material for the warehouse is done from the external vendor through the project A & with the wbs element A.01 through the project stock 'Q'

2. Once the material is available at warehouse (Q stock against the WBS A.1 is stored through the GRN),

3. Stock transfer order created from warehouse to one of the intra site(plant) through the project B agsinst the WBS element B.01. Replinshment delivery created , further to this while creating Transfer order, system is through the negative quantity & supplying wbs is displayed as B.01. (instead of A.01).

So please let me , if any settings needs to be changed.

Regards