Hi All

We are running actual Assessment cycle KSU5. When we try to run for only secondry cost elements, for plan data, it is not picking sender values. When I run the report S_ALR_87013611 - Cost Centers: Actual/Plan/Variance , I can see that there is plan cost in the system.

KP07 also is not showing any data for Secondry cost element.

Can some one help us with where this plan data is comming in the variance report but not getting picked in Assessment and KP07.