on 11-24-2011 9:24 AM
Hi,
I have added Amount key figure using remodelling and gave a constant value. When i try to schedule it i am getting this error
Please add unit to the key figure. Add 0Currency but 0cuurency has been assigned to the key figure infoobject
Thanks in advance
krish
Hi
Can u tell me when ur getting the error? I think u won't get any error of datatype because ur adding constant value . Can u tell me what are the steps have u performed .
Thanx & Regards,
RaviChandra
Edited by: Ravichandra.bi on Nov 24, 2011 1:09 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
when you are trying to schedule it add the currency(like $) to the field in the source file.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As you are assigning constant value then why don't you assign constant Unit value as well. Just try assigning constant unit value.
Regards,
Durgesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.