Hello Gurus,
Shift pattern - 14 day shift
I would like to add a 14 day shift pattern into the resource within SAP.
The "length of the cycle" would be 14 days, however the system displays
an error message stating that only 1 or 7 days is valid.
The actual working days would be Monday, Tuesday, Wednesday, Thursday,
Friday, then Monday, Tuesday, Wednesday, and Thursday ( 9 days working
out of a possible 14 days)
How to get it done?
and Can the cycle length be changed to allow 14 days? then this problem can be tackeled.
Thanks in Advance,
Sap User