Shift pattern in Resource - 14 day shift mapping

Former Member
0 Kudos

Hello Gurus,

Shift pattern - 14 day shift

I would like to add a 14 day shift pattern into the resource within SAP.

The "length of the cycle" would be 14 days, however the system displays

an error message stating that only 1 or 7 days is valid.

The actual working days would be Monday, Tuesday, Wednesday, Thursday,

Friday, then Monday, Tuesday, Wednesday, and Thursday ( 9 days working

out of a possible 14 days)

How to get it done?

and Can the cycle length be changed to allow 14 days? then this problem can be tackeled.

Thanks in Advance,

Sap User

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Gautam,

What can be possible way to achieve this , as this is a genuine requirement , I have thought for using the factory calendar with assignment of new holiday calendar with alternate Friday as Holiday. But is there any other way out to tackle this complex shift pattern.

Regards,

Sap user

former_member311826
Active Contributor
0 Kudos

Dear,

Cycle length cannot be greater than 7 days. you need to find other way for this.

Regards

Abhijit Gautam