Nov 22, 2011 at 01:15 PM

Requirements date for VSF "backdating" itself in two months

60 Views

Please help me understand this peculiar system behavior.

MD04 routinely displays the plant/materialu2019s planned independent requirement as a u201CVSFu201D having a requirements date of the first work-day of the period. What I cannot explain is why the October 2012 VSF has a requirements date of September 21, 2012. Why would the date not be October 1, 2012? The factory calendar assigned to the plant has October 1, 2012 as a work-day.

Same situation for December 2012. The VSF for December has a requirements date of November 21, 2012.

For the rest of 2012, and for the first three months of 2013, the VSF elements are dated on the first work-day of the month. What would cause the requirements to fall a week and a half early for October and December 2012?

I should add that this peculiarity is not limited to one material. It happens over many materials and across all plants. The common thread among the materials is that we plan them into info structure S608 and then disaggregate among the active warehouses / shipping points.

By the way, I am not very fluent in MRP, so please do not assume that I have ruled out something obvious.

Regards,

zKen