Problem with refurbishment settlement

Former Member
0 Kudos

Hi,

I have a problem with the refurbishment settlement.

I want to refurbish an article with a moving price of 100u20AC. There is 2 articles in the warehouse.

This is the process :

1. Good receipt in warehouse of the article to refurbished MIGO

2. Refurbishment order creation with external maintenance (PM02) IW81. Cost of maintenance of 50u20AC.

3. Purchase order for the prestation ME21N

4. Good issue on order to the supplier MIGO

5. Good receipt IW8W

6. Settlement KO88

The article should be incorporate in the warehouse at a price of 50u20AC (cost of maintenance) and the moving price should be 75u20AC.

But the article is incorporated at a price of 150u20AC (moving price+maintenance cost) and the moving price is 125u20AC.

Can someone tell me what is the problem in my process ? Did i forgot something ? Or maybe should i forgot to customize something for the settlement ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I think, the problem is with settlement rules defined. now your both moving price and artical refurbishment prices are being settled into article itself. usually, movement cost should be settled to respective cost centre. hope it will solve your issue.

Regards,

Lucky

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

I would suggest u to check this link to understand calculation of refurbishment cost calculation :

regards

pushpa

Former Member
0 Kudos

Thanks, but we dont have valuation type for this article. And we would want if possible to not use valuation type.

Do you think it's a requirement for refurbishment ?