Error in Project Progress Config and process steps

162 Views

Hi experts,

I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.

I am using CJ40, CJ30 and CJ32.

IN IMG i have configured like given below

1. I have created Progress version 100

EV base - Cost Plan ( active Proejct, Annual Value)

POC weighting - Weight

Planning type - Basic dates

Early/Late - Earliest Possible

Actual method and Ref plan method tick.

2. Measurement method -

for cost based report i have selected - Cost proportional

3. Default value for measuremnt method -

100 -WBS element - Plan - Cost proportional

100 - WBS element - Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

100 - Acitvity ( int)- Actual - Cost proportional

I have put this in CJ20N. I followed following steps

1. CNE1

2. CNE5

but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion

can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.

Thanks,