Hi experts,
I am implementing PS for Asset procurement, in this i will procure material against material component which is added in Internal activity. I am using scheduling also. Now My client requirement is that he want project progress report on cost basic.
I am using CJ40, CJ30 and CJ32.
IN IMG i have configured like given below
1. I have created Progress version 100
EV base - Cost Plan ( active Proejct, Annual Value)
POC weighting - Weight
Planning type - Basic dates
Early/Late - Earliest Possible
Actual method and Ref plan method tick.
2. Measurement method -
for cost based report i have selected - Cost proportional
3. Default value for measuremnt method -
100 -WBS element - Plan - Cost proportional
100 - WBS element - Actual - Cost proportional
100 - Acitvity ( int)- Actual - Cost proportional
100 - Acitvity ( int)- Actual - Cost proportional
I have put this in CJ20N. I followed following steps
1. CNE1
2. CNE5
but it is showing 0 value in all tabs such as Aggregate planned percentage of completion, Non-aggregated planned percentage of completion
can anyone tell me the total process to get this report perfectly. It is very urgent need so please help me guys.
Thanks,