How do I confirm the dates and quantity of material PRT I used for a network activity? I have confirmed the activity to which a material PRT was assigned. The actual dates are not getting copied to PRT nor do I have a possibility to edit the quantity or actual dates of PRT usage during activity confirmation. Pls Advise!

Thanks,

Nithin.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Nov 22, 2011 at 05:32 AM

    Hi,

    I just went through SAP Help and found useful info that may answer your query. Suggest you to go through the PRT section in SAP Help and then come back with specific queries.

    Regards,

    Gokul

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hello Gokul,

      Am afraid I couldn't find anything in SAP help regarding actual quantity or confirmation of PRTs. The documentation that is available talks about creation, assignment, deletion, availability check etc. It doesn't explain how to enter actual quantities.

      Question was specific!

      How to enter actual usage quantity of a material PRT during an activity confirmation? Pls help!

      Thanks,

      Nithin.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.