Hello All,
How do I confirm the dates and quantity of material PRT I used for a network activity? I have confirmed the activity to which a material PRT was assigned. The actual dates are not getting copied to PRT nor do I have a possibility to edit the quantity or actual dates of PRT usage during activity confirmation. Pls Advise!